|
After moving in the first room to get finished was the bathroom. We started by creating the partitions needed |
|
Then drywall and painting |
|
all the fixtures |
|
the counter for the sink |
|
and the shower. |
|
The master bedroom was commendeered as the workshop while we were doing all the finish work, as it was the only room big enough to allow us to cut a sheet of plywood, and had a door to keep down the dust |
|
While the bedroom was in use as a workshop, we put the bed in the future library |
|
The next big project was the kitchen cupboards, which were entirely built on site. We started with a base made of 2x4s screwed to the floor |
|
and then proceeded to make the boxes out of 3/4" paint grade plywood. |
|
We then added the support for the counter tops. |
|
Before we put the finished countertops in, we had the taping done on the ceiling. This is one of the jobs I contracted out, as 1) I didn't have the time since I was working at an outside job by this point and 2)I hate taping ceilings and 3) I knew I couldn't do as good a job as I wanted on the butt seams. |
|
After the ceilings were done, I proceeded to make the boxes for the drawers in the kitchen and installed them. |
|
After the boxes were finished, I made the doors and drawer fronts from maple and plywood. The finshed kitchen counters are made of cherry flooring and coated with 6 coats of Varathane. |
|
The kitchen was designed with short section of countertop that was about 6 inches lower than normal to create a bake center. This counter is the correct height to comfortably kneed dough, and has a granite countertop to keep the surface cool. |
|
Since we were taking our time doing the finishing, we had time to figure out how we wanted things done and had time to find interesing lighting for the library, |
|
guest bedroom |
|
and stairwell. |
|
After all the drywall was in and painted |
|
we then moved on to building the window seats |
|
installing the pine plank floor, |
|
and installing the trim. The window jambs were made from plywood, cut to fit and the casing was made from 1x4 pine and then painted. |
|
The door jambs were also made from plywood. |
|
and the doors were installed. We were going to make the doors, but decided to buy premade doors when we found them at a local lumberyard for less than the materials to make them. |
|
One of the final jobs was the installation of the flooring |
|
We chose a plank vinyl flooring. I wasn't crazy about using vinyl as I had avoided using it in the house up to this point, but we had to make a compromise in order to get the look we wanted and still not have something that would insulate the infloor heating. |
|
The final job was to finish off the library. |
|
At this point we could sit back and enjoy, at least until we start work on the landscaping. |
|
Kitchen |
|
Kitchen and Dining |
|
Kitchen |
|
Library |
|
By the stairwell |
|
Master Bedroom |
|
Sitting area upstairs |
|
Sitting area upstairs |
|
Guest Bedroom |
|
Upstairs Bathroom |
|
The cat thinks it's ok too. |